Week of November 29, 2021
PHASE 2: Construction Wrapping Up
The project will be completed this Friday with the exception of a few miscellaneous items, such as crosswalk striping and a few signs. Traffic Control will be cleaned up by this time and any work connected to the remaining items will not affect public access to the area.
2-WEEK LOOK AHEAD
Week of November 15, 2021
PHASE 2: Construction Update
This week, Scott & Murphy Inc. will be focusing on the following tasks:
Monday-Friday
-
Continue the lane closure on College Street between 7th Street and Main Street.
-
Continue Demolition along College Street.
-
Continue installation of curb, sidewalks, and entrances along College Street.
The following contractors will be focusing on the following tasks:
Aquamatics; Monday-Friday
-
Begin excavation/backfill of landscape areas along East Main Street between College Street and Center Street.
-
Complete the installation of plants, stone mulch, and sod along State Street.


Week of November 8, 2021
PHASE 2: Construction Update
This week, Scott & Murphy Inc. will be focusing on the following tasks:
Monday-Friday
-
Lane closures will continue at East Main Street.
-
Continue constructing sidewalks and curb & gutter in demolition areas on East Main Street between College Street and Center Street.
-
Continue the lane closure on College Street between 6th and 7th Streets.
-
Continue Demolition and installation of curb & gutter/landscaping bump-outs.
The following contractors will be focusing on the following tasks:
Aquamatics; Monday-Friday
-
Begin installation of stone mulch and sod in landscape areas along East Main Street between State Street and Chestnut Street.



Week of November 1, 2021
PHASE 2: Construction Update
This week, Scott & Murphy Inc. will be focusing on the following tasks:
Monday-Friday
-
Lane closures will continue at East Main Street.
-
Continue constructing sidewalks and curb & gutter in demolition areas on East Main Street between College Street and Center Street.
-
Continue the lane closure on College Street between 6th and 7th Streets.
-
Continue Demolition and installation of curb & gutter/landscaping bump-outs.
The following contractors will be focusing on the following tasks:
Aquamatics; Monday-Friday
-
Continue installation of plants and stone in landscape areas along East Main Street between State Street and Chestnut Street.



Week of October 25, 2021
PHASE 2: Construction Update
This week, Scott & Murphy Inc. will be focusing on the following tasks:
Monday-Friday
-
Lane closures will continue at East Main Street.
-
Continue constructing sidewalks and curb & gutter in demolition areas on East Main Street between College Street and Center Street.
-
Set up a lane closure on College Street between 6th and 7th Streets.
-
Begin Demolition and installation of curb & gutter/landscaping bump-outs.
The following contractors will be focusing on the following tasks:
Aquamatics; Monday-Friday
-
Begin installation of plants and stone in landscape areas along East Main Street between State Street and Chestnut Street.
Scotty's Contracting; Monday-Tuesday
-
Complete asphalt paving on State Street between 6th and 7th Streets.
Reynolds Striping; Tuesday-Wednesday
-
Place permanent striping on new asphalt along State Street and East Main Street.



Week of October 18, 2021
PHASE 2: Construction Update
**Please note that due to a couple of weather events that we had last week we were delayed in getting the paving for State St., backfilling, and sidewalks completed on East Main between State St. and Chestnut St.**
This week, Scott & Murphy Inc. will be focusing on the following tasks:
Monday-Tuesday
-
Continue the layout of project along College Street.
-
Lane closures will continue at East Main Street.
-
Completion of constructing sidewalks, curb and gutter, and concrete paving in demolition areas on East Main Street.
Tuesday-Friday
-
Set up of lane closure on East Main Street between College Street and Center Street.
-
Begin demolition of curb & gutter and sidewalks along East Main Street.
The following contractors will be focusing on the following tasks:
Aquamatics; Monday-Friday
-
Complete the excavation and backfill of sidewalks, curb & gutter, and landscape areas along East Main Street between State Street and Chestnut Street.
Scotty's Contracting; Wednesday-Thursday
-
Begin milling operations on State Street and East Main Street.
Friday-Saturday
-
Complete asphalt paving on State Street and East Main Street.
Reynolds Striping; Friday-Saturday
-
Place permanent striping on new asphalt along State Street and East Main Street.



Week of October 11, 2021
PHASE 2: Project continues on East Main Street.
This week, Scott & Murphy Inc. will be focusing on the following tasks:
Monday-Wednesday
-
Continue the layout of project along College Street.
-
Lane closures will continue at East Main Street.
-
Completion of constructing sidewalks, curb and gutter, and concrete paving in demolition areas on East Main Street.
Wednesday-Friday
-
Set up of lane closure on College Street Beginning at 6th Avenue.
-
Begin demolition of curb & gutter and sidewalks along College Street.
The following contractors will be focusing on the these tasks:
Aquamatics; Monday-Friday
-
Complete the excavation and backfill of sidewalks, curb & gutter, and landscape areas along East Main Street.
Scotty's Contracting; Wednesday-Thursday
-
Begin milling operations on State Street and East Main St.
Friday-Saturday
-
Complete asphalt paving on State Street and East Main St.
Reynolds Striping; Friday-Saturday
-
Place permanent striping on new asphalt along State Street and East Main St.



Week of October 4, 2021
PHASE 2: Project continues on East Main Street.
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Begin layout of project along College Street.
-
Lane closures will continue at East Main Street.
-
Continue demolition of East Main Street in front of US Bank.
-
Continue constructing sidewalks, curb and gutter, and concrete paving in demolition areas on East Main Street in front of US Bank.
This week, AquaMatics will be focusing on the following tasks: -
Begin excavation and backfill of sidewalks, curb & gutter, and landscape areas along East Main Street.
-
Complete the backfill of sidewalks, curb & gutter, and landscape areas along State Street.


Week of September 27, 2021
PHASE 2: Project continues on Main;
AquaMatics works on State Street.
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along Main Street.
-
Completion of the remaining sidewalks at the intersection of State Street and 7th Ave.
-
Lane closure will continue at East Main Street.
-
Continue demolition of East Main Street in front of US Bank.
-
Begin constructing sidewalks, curb and gutter, and concrete paving in demolition areas on East Main Street in front of US Bank.
This week, AquaMatics will be focusing on the following tasks:
-
Continue excavation of landscape areas along State Street.
-
Continue the backfill of sidewalks, curb & gutter, and landscape areas along State Street.



Week of September 20, 2021
PHASE 2: Project begins on Main;
AquaMatics works on State Street.
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Begin layout of project along Main Street.
-
The lane closure in the right lane of State Street will continue from 7th Avenue to 6th Avenue.
-
Continue the demolition of the corners at the intersection of State and 7th Avenue.
-
Completion of the remaining sidewalks on State Street.
-
Set up a lane closure at East Main Street.
-
Begin demolition of East Main Street in front of US Bank.
-
Begin constructing sidewalks, curb and gutter, and concrete paving in demolition areas on East Main Street in front of US Bank.
This week, AquaMatics will be focusing on the following tasks:
-
Begin excavation of landscape areas along State Street.
-
Begin backfill of sidewalks and curb & gutter along State Street.



Week of September 13, 2021
PHASE 2: Disturbance continues on State Street
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
The lane closure in the right lane of State Street will continue from 7hth Avenue to 6th Avenue.
-
Continue demolition of the East side of State Street from 7th Avenue working toward 6th Avenue.
-
Continue constructing sidewalks, curb and gutter, and concrete paving in demolition areas in the right lane of State Street.


Week of September 6, 2021
PHASE 2
Disturbance continues down State Street
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
The lane closure in the right lane of State Street will continue from 8th Avenue to 6th Avenue.
-
Continue demolition of the East side of State Street from 7th Avenue working toward 6th Avenue.
-
Continue constructing sidewalks, curb and gutter, and concrete paving in demolition areas in the right lane of State Street.


Week of August 30, 2021
PHASE 2
Disturbance continues down State Street
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
The lane closure in the right lane of State Street will continue from 8th Avenue to 6th Avenue.
-
Continue demolition of the East side of State Street from 7th Avenue working toward 6th Avenue.
-
Continue constructing sidewalks, curb and gutter, and concrete paving in demolition areas in the right lane of State Street.


Week of August 23, 2021
PHASE 2
Disturbance continues down State Street
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
The lane closure in the right lane of State Street will continue from Main Avenue to 7th Avenue.
-
Concrete paving for parallel parking near Spring Alley will be completed.
-
Continue demolition of the East side of State Street beginning at Spring Alley working toward 7th Avenue.
-
Continue constructing sidewalks, curb and gutter, and concrete paving in demolition areas in the right lane of State Street.


Week of August 16, 2021
PHASE 2
Disturbance further down State Street
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
Set up a lane closure in the right lane of State Street from Main Avenue to 7th Avenue.
-
Begin demolition of the East side of State Street beginning at Spring Alley working toward 7th Avenue.
-
Begin constructing sidewalks, curb and gutter, and concrete paving in demolition areas.


Week of August 9, 2021
PHASE 2
Continuing work on State St
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
Continue a lane closure on the Northwest lane of State Street between 7th and 8th Avenues.
-
Continue the installation of the bump-out curbs and corners on the Northwest side of State Street from 7th Ave. to 6th Ave.


Week of August 2, 2021
PHASE 2
Continuing work on State St
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
Set up a lane closure in the East lane of 8th Ave.
-
Complete the placement of curb and gutter along East lane of 8th Avenue.
-
Complete the placement of the sidewalk and ADA ramps on the North corner of State Street and 8th Avenue.
-
Set up a lane closure on the Northwest lane of State Street between 7th and 8th Avenues.
-
Begin the installation of the bump-out curbs and corners on the Northwest side of State Street from 7th Ave. to 6th Ave.



Week of July 26, 2021
PHASE 2
Continuing work on State St
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
Set up a lane closure in the West lane of 8th Ave.
-
Complete the placement of entrances on 8th Ave.
-
Set up a lane closure on the Northwest lane of State Street.
-
Begin the installation of the bump-out curbs and corners on the Northwest side of State Street from 8th Ave. to 6th Ave.



Week of July 19, 2021
PHASE 2
New Sidewalks on 8th Ave
This week, Scott & Murphy Inc. will be focusing on the following tasks:
-
Continue layout of project along State Street.
-
Set up a lane closure in the West lane of 8th Ave.
-
Continue demolition of the project on the West side of 8th Ave.
-
Place new sidewalks at the corner of State Street and 8th Avenue. Continue installation of sidewalks on the West side of 8th Avenue from Heritage Trail to College Street.


Week of June 21, 2021
PHASE 2
CONSTRUCTION TO BEGIN
From Monday, 6/21, to Friday, 6/25, Scott & Murphy Inc. will be focusing on the following tasks:
-
Begin layout of project.
-
Begin mobilization of equipment and materials to the project site.
-
Setting up a lane closure in the left lane of State Street between Main St. and 8th Ave.
-
Setting up a temporary closure of Spring Alley.
(Estimated Closure to be three working days).
-
Begin demolition of the project at the intersection of Spring Alley working toward 8th Ave.